November 08- Approval complete from PPS
November/December 08- Finalize Design Plan and budgets; Begin Monthly BDS Review.
November-January 08/09- Fundraising Phase I
January-April 09- Fundraising Phase II
February 09- Prepare Construction Documents
March 09- Submit Plans to PPS
April 09- Plans to City for Building Permit
June 09- Groundbreaking
August 09- Completion and Dedication